When we looked at our WBS, it has the headings on here.
And if we go into a Gantt chart, we can also put those headings on here.
The headings typically do not go on a network diagram, but on a Gantt chart,
you're often gonna see those, and those are those
big dark bars across a group of tasks, and they're called summary tasks.
That's the heading, like start the day, clothing, food,
those actually show up on a Gantt chart, typically.
Here on our Gantt chart,
we also see the critical path of the project and we see the float time.
All of those red tasks are the critical path of the project,
ending with a milestone put on the Gantt chart as a little diamond shape,
little diamond shaped piece.
And the float time across there shows up in blue.
We are told that we wanna see it in different color.
Gantt chart, what do we see on a Gantt chart?
Early start, early finish,
past duration.
The connecting lines that we see on there.
They're exactly the same connecting lines that we've seen before,
either a dependency line or a predecessor line.
We'll say this task is followed by another task.
That task is dependent.
If we say this task had something happen before then we talked about
a predecessor line.